Q1: PERT stands for

A Programme Estimation and Reporting Technique

B Process Estimation and Review Technique

C Programme Evaluation and Review Technique

D Planning Estimation and Resulting Technique

ANS:C - Programme Evaluation and Review Technique

Explanation: No answer description is available. 