A critical ratio scheduling

A establishes the relative priorities among various activities on a common basis

B determines the status of each activity

C adjusts automatically changes in activity progress

D is a dynamic system

E none of these.

ANS:E - none of these.

Critical Ratio Scheduling is the Technique for establishing & maintaining priorities among the various jobs of a project.

Hence option A is correct.