Q1:

A dummy activity

A is artificially introduced

B is represented by a dotted line

C does not consume time

D all the above.

ANS:D - all the above.

A Dummy activity is a type of operation in a project network that neither requires any time nor any resource. It is an imaginary activity shown in a project network to identify the dependence among operations.