Industrial Engineering and Production Management - Engineering

Q1:

A dummy activity becomes a critical activity when its earliest start time (EST) is same as its latest finishing time (LFT).

A Correct

B Incorrect

ANS:A - Correct

Explanation: No answer description is available.