Q1: A feasible solution to the linear programming problem shouldA satisfy the problem constraints
B optimise the objective function
C satisfy the problem constraints and non-negativity restrictions
D satisfy the non-negativity restrictions
ANS:C - satisfy the problem constraints and non-negativity restrictions Explanation: No answer description is available. |