Construction Management - Engineering

Q1:

A Milestone chart

A shows the interdependencies of various jobs

B depicts the delay of jobs, if any

C points outgoing ahead of schedule of jobs, if any

D none of these.

ANS:D - none of these.

It is a modification over the original Gantt (Bar) chart. Milestones are key events of main activities represented by the bar.