UPSC Civil Service Exam Questions - Engineering

Q1:

Consider the AoA network of a project shown in the given figure. (Activities are designated by alphabets and durations are shown around the stem of the arrow.) The critical path will be

A 1-2-3-6-7-8

B 1-2-3-5-7-8

C 1-2-4-5-7-8

D 1-2-4-6-7-8

ANS:B - 1-2-3-5-7-8

No answer description is available.