Q1: Consider the implicit details between, before and after successive steps in/within the order while doing time computations on a CPM network. (FP => Forward Pass; BP => Backward Pass; LET => Late Event Time; EET => Early Event Time; TF => Total Float; PD => Project Duration; AD => Activity Duration)
The correct sequence of computation would be

A EET, PD, LET, TF

B EET, PD, LET, AD

C AD, EET, BP, PD

D FP, EET, TF, PD

ANS:C - AD, EET, BP, PD

No answer description is available.