Q1: Critical path lies along the activities having total floatA
positive
B
negative
C
zero
D
same.
ANS:C - zero The critical path consists of activities that have zero total floats. Total float, also known as slack, refers to the amount of time an activity can be delayed without affecting the project's overall duration. |