Construction Management

Q1: Critical path lies along the activities having total float

A positive

B negative

C zero

D same.

ANS:C - zero

The critical path consists of activities that have zero total floats. Total float, also known as slack, refers to the amount of time an activity can be delayed without affecting the project's overall duration.

Activities on the critical path have zero total floats, which means any delay in these activities would directly impact the project's completion time. Therefore, the correct statement is that the critical path lies along the activities having zero total floats.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.