UPSC Civil Service Exam Questions

Q1: Duration along the critical path defines which of the following ?
1. Shortest duration needed
2. Shortest duration permissible
3. Longest duration needed
4. Longest duration permissible
Select the correct answer using the code given below :

A 1 and 2 only

B 1 and 4 only

C 2 and 3 only

D 3 and 4 only

ANS:B - 1 and 4 only

Duration along the critical path defines the project duration. By proper planning it can be made as short as possible. Hence shorter duration is needed to complete the project in shortest time possible.

It is the maximum duration path hence the longest duration is permissible along the critical path in comparison to other path available from start to end.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.