Q1: Earliest finish time can be regarded as

A earliest start time + duration of activity

B earliest start time - duration of activity

C latest finish time + duration of activity

D latest finish time - duration of activity

ANS:A - earliest start time + duration of activity

Explanation: No answer description is available. 