Q1: Earliest finish time can be regarded asA earliest start time + duration of activity
B earliest start time - duration of activity
C latest finish time + duration of activity
D latest finish time - duration of activity
ANS:A - earliest start time + duration of activity Explanation: No answer description is available. |