Waste Water Engineering

Q1: For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance of

A 100 cm

B 120 cm

C 140 cm

D 160 cm

E 180 cm

ANS:D - 160 cm

To determine the distance at which an offset line is marked parallel to the given centerline for laying a sewer line in a trench of 2 m width, we need to consider the half-width of the trench. Given:

  • Trench width = 2 m
The half-width of the trench would be half of 2 m, which is 1 m. Now, let's convert 1 m to centimeters: 1 meter=100 centimeters1meter=100centimeters So, the offset line should be marked at a distance of 100 cm100cm from the centerline, parallel to the given centerline. Therefore, the correct option is 100 cm.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.