 
             
            Waste Water Engineering - Engineering
| Q1: For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance ofA 
                                                    
                                                        100 cm
                                                    
                                   B 
                                                    
                                                        120 cm
                                                    
                                   C 
                                                    
                                                        140 cm
                                                    
                                   D 
                                                    
                                                        160 cm
                                                    
                                   E 
                                                    
                                                        180 cm
                                                    
                                   ANS:D - 160 cm To determine the distance at which an offset line is marked parallel to the given centerline for laying a sewer line in a trench of 2 m width, we need to consider the half-width of the trench. Given: 
 | 
 
             
                            
                                    For help Students Orientation 
                                    Mcqs Questions
                                
                                One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.
 
                            