Q1: For laying a sewer line in a trench of 2 m width, an offset line is marked on the ground parallel to the given centre line at a distance ofA
100 cm
B
120 cm
C
140 cm
D
160 cm
E
180 cm
ANS:D - 160 cm To determine the distance at which an offset line is marked parallel to the given centerline for laying a sewer line in a trench of 2 m width, we need to consider the half-width of the trench. Given:
|