UPSC Civil Service Exam Questions - Engineering

Q1:

For the network shown in the above figure (the number on each arrow denotes the time duration of activity in days), the earliest star time, in days for activity 5-6 is

A 8

B 7

C 9

D 11

ANS:A - 8

Option C is the correct answer. Please explain me.