Construction Management - Engineering
Q1: For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, isA 1
B 2
C 3
D 4
ANS:A - 1 Concrete work is an activity. |