Q1:

For the supply of materials for concrete, form work reinforcing and placing of concrete, removal of form work and curing of concrete, number of bar(s) required on bar chart, is

A 1

B 2

C 3

D 4

ANS:A - 1

Concrete work is an activity.

And, The various functions under each activity are shown by one bar on a bar chart.

So, Concrete work is an activity and others are functions.

So, No of bars will be 1.