Time and Work - General Aptitude
Each of the questions given below consists of a question followed by three statements. You have to study the question and the statements and decide which of the statement(s) is/are necessary to answer the question.
Q1: How many workers are required for completing the construction work in 10 days? I. 20% of the work can be completed by 8 workers in 8 days. II. 20 workers can complete the work in 16 days. III. One-eighth of the work can be completed by 8 workers in 5 days.A
I only
B
II and III only
C
III only
D
I and III only
E Any one of the three
ANS:E - Any one of the three
![]()
![]()
![]()
![]() ![]() |