Q1: If D is the diameter of upper circular portion, the overall depth of New Egg shaped sewer section, isA
1.250 D
B
1.350 D
C
1.425 D
D
1.625 D.
ANS:D - 1.625 D. The overall depth of a new egg-shaped sewer section can be expressed in terms of the diameter of the upper circular portion (D). The egg-shaped sewer section typically consists of a circular upper portion and a lower elliptical or egg-shaped portion. The relationship between the diameter of the upper circular portion (D) and the overall depth of the sewer section can be expressed as follows: Overall Depth=k×D where k is a constant factor that depends on the specific design of the egg-shaped sewer section. The value of k can vary depending on the specific design standards or specifications used. However, commonly used values for k range between approximately 1.25 to 1.75. Given the options provided, let's try each one using the diameter of the upper circular portion (D):
|


For help Students Orientation
Mcqs Questions
One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.