Industrial Engineering and Production Management - Engineering

Q1:

If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Halsey 50-50 plan, wages for the job will be

A TR

B

C TR + (S - T)R

D

ANS:B -

Explanation: No answer description is available.