Construction Management - Engineering

Q1:

If the total float and duration of an activity are 5 and 10 days respectively, the particular activity can be

A started 5 days later

B completed 5 days later

C performed at slower rate in 15 days

D all the above.

ANS:D - all the above.

@Amit @Loai.

Total float means the time that can be a delay which doesn't affect the estimated completion duration.