Q1: In a network shown in the below figure, the critical path is along A 1-2-3-4-8-9
B 1-2-3-5-6-7-8-9
C 1-2-3-4-7-8-9
D 1-2-5-6-7-8-9
ANS:B - 1-2-3-5-6-7-8-9 Explanation: No answer description is available. |