Construction Management - Engineering
Q1: In CPM analysis,A
emphasis is given to activities
B
uncertainties are not allowed
C
activities are represented by arrows
D
beginning and end of an activity, are denoted by nodes
E
all the above.
ANS:E - all the above. No answer description is available. |