UPSC Civil Service Exam Questions

Q1: In PERT, the actual time duration along the critical path for the project completion time is probabilistic. It is usually presumed to follow which one of the following ?

A Beta distribution

B Poisson distribution

C Normal distribution

D Log-normal distribution.

ANS:A - Beta distribution

Option C is the correct answer.

For pert, the Normal distribution is correct for the whole project, and individual activity follows the beta distribution.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.