UPSC Civil Service Exam Questions

Q1:
In the network given in figure, the maximum number of shovels and dumpers required are

A 6 shovels and 14 dumpers on days 9 and 10

B 24 shovels and 10 dumpers on days 3 and 4

C 30 shovels and 90 dumpers on all days

D 10 shovels and 24 dumpers on days 3 and 4

ANS:D - 10 shovels and 24 dumpers on days 3 and 4

Activity 1-2 and 1-3 are parallel activity and run parallel for 2 days as the duration for 1-2 is 2 days so for this time no of shovel required =1+3=4.

And no of dumper reqd =4+8=12.

Now, activities 1-2 finish after 3 days and 1-3 continue with 2-3 and 2-4 for the remaining 2 days.
So no of shovel reqd=3+4+3=10.
No dumper required =8+4+12=24.

After 1-3 is complete activity 2-3 and 2-4 runs for 2 days as after 2 days activity 2-3 will finish.

So, no of shovel reqd= 4+3=7.
No of dumper reqd=4+12=16.

In a similar manner requirement of shovel and dumper can be computed for remaining activities.

Thanks.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.