Q1: PERT stands forA Programme Estimation and Reporting Technique
B Process Estimation and Review Technique
C Programme Evaluation and Review Technique
D Planning Estimation and Resulting Technique
ANS:C - Programme Evaluation and Review Technique Explanation: No answer description is available. |