Engineering Economy

Q1: Pick up the correct reason for making conceptual (or preliminary) estimate from the following:

A To have a check on a definitive cost estimate.

B To check qoutations from contractors and/or sub contractors.

C To compute target estimate for the owner while drawings and specifications are in initial stage.

D All of these.

ANS:D - All of these.

No answer description is available. 