Irrigation

Q1: Pick up the correct sequence of the part of a canal system from the following

A Head work-distributary-branch canal-minor

B Head works-main canal-branch canal-dis-tributary-minor

C Head works-main canal-branch canal-minor-distributary

D Heads works-branch canal-main canal distributary, minor.

ANS:B - Head works-main canal-branch canal-dis-tributary-minor

It is Head work- Main canal-branch-distributary-minor-field channel.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.