Irrigation - Engineering
Q1: Pick up the correct sequence of the part of a canal system from the followingA Head work-distributary-branch canal-minor
B Head works-main canal-branch canal-dis-tributary-minor
C Head works-main canal-branch canal-minor-distributary
D
Heads works-branch canal-main canal distributary, minor.
ANS:B - Head works-main canal-branch canal-dis-tributary-minor It is Head work- Main canal-branch-distributary-minor-field channel. |