Irrigation - Engineering

Q1:

Pick up the correct statement from the following

A In a level crossing, a crest with its top at the canal F.S.L. is provided across the drainage at its up-stream junction with canal

B In a level crossing a regulator is provided across the drainage at its down-stream

C In a level crossing, a cross regulator is provided on the canal below the crossing

D All the above.

ANS:D - All the above.

No answer description is available.