Construction Management - Engineering

Q1:

Pick up the correct statement from the following:

A CPM analysis is activity oriented

B PERT analysis is event oriented

C CPM does not make any allowance for the uncertainties in the duration of time

D In CPM, the time is related to cost

E All the above.

ANS:E - All the above.

How is option D is possible? Please explain clearly.