Construction Management

Q1: Pick up the correct statement from the following:

A The difference of latest occurence time and earliest expected time, is called slack

B The activities connecting the events having zero slack, lie on the critical path

C The critical path consumes the maximum time

D All the above.

ANS:D - All the above.

Critical path.

It is the sequence of critical activities, which decide the total project duration. A critical path consumes maximum resources. It is the longest path and consumes maximum time. It is the one, which connects the events having zero minimum float.



img not found
img

For help Students Orientation
Mcqs Questions