Construction Management - Engineering

Q1:

Pick up the correct statement from the following:

A The difference of latest occurence time and earliest expected time, is called slack

B The activities connecting the events having zero slack, lie on the critical path

C The critical path consumes the maximum time

D All the above.

ANS:D - All the above.

Critical path.

It is the sequence of critical activities, which decide the total project duration. A critical path consumes maximum resources. It is the longest path and consumes maximum time. It is the one, which connects the events having zero minimum float.