

Construction Management - Engineering
Q1: Pick up the correct statement from the following:A
The difference of latest occurence time and earliest expected time, is called slack
B
The activities connecting the events having zero slack, lie on the critical path
C
The critical path consumes the maximum time
D
All the above.
ANS:D - All the above. Critical path. |


For help Students Orientation
Mcqs Questions
One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.