Q1: Pick up the correct statement from the following:

A The duration between the earliest start time of the preceding event and latest finish time of the succeeding event, is called 'float'

B The duration of time by which an activity can be delayed without affecting the succeeding activity, is called free float

C The float which affects neither the processor nor the successor activities, is called independent float

D The difference between total float and free float, is called interfering float

E All the above.

ANS:E - All the above.

Optin B, and C are the definitions, so these two are correct.