Construction Management - Engineering

Q1:

Pick up the correct statement from the following:

A Programme Evaluation and Review Technique, is event oriented

B Programme Evaluation and Review Technique is not event oriented

C Critical Path Method is event oriented

D Critical Path method is event oriented.

ANS:A - Programme Evaluation and Review Technique, is event oriented

PERT : Event-oriented.

CPM : Activity oriented.