Pick up the correct statement from the following:

A The earth work of cutting in trenches or borrow pits in fairly uniform ground is measured with the help of average depths of the dead men

B The earth work in trenches or borrow pits in irregular ground is measured by taking the difference in levels before and after completion of work

C The earth work in trenches or borrow pits, where neither a nor b is feasible, are measured from the fillings after deduction of voids

D All the above.

ANS:D - All the above.

No answer description is available.