Q1: Pick up the correct statement from the following with regards to C.P.M. network analysis of projectsA
Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity
B Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity
C
The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time
D
The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time
E
All the above.
ANS:E - All the above. No answer description is available. |