Construction Management

Q1: Pick up the correct statement from the following with regards to C.P.M. network analysis of projects

A Earliest occurrence time of the event from which the activity arrow' originates, is called earliest start time of the activity

B Earliest occurrence time of the event from which the activity arrow originates plus the duration of the activity, is called earliest finish time of the activity

C The latest occurrence time of the node of which the activity arrow terminates minus the duration of the activity, is called latest start time

D The latest occurrence time for the node at which the activity arrow terminates, is called latest finish time

E All the above.

ANS:E - All the above.

No answer description is available.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.