Q1: Pick up the correct statement regarding the centre line method of estimating a building

A Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item

B The centre line is worked out separately for different sections of walls of a building

C The centre line length is reduced by half the layer of main wall joining the partition wall

D All the above.

ANS:D - All the above.