Q1: Pick up the incorrect statement from the following:

A An activity of a project is denoted by an arrow on the net work

B The tail of the arrow indicates the start of the activity

C The head of the arrow indicates the end of the activity

D The arrows are drawn to scale from left to right

E Each activity consumes a given time.

ANS:D - The arrows are drawn to scale from left to right

D is the correct answer because.

Duration of the activities are representing from left to the right.