Q1: Pick up the incorrect statement from the following:

A The activity is the time consuming part of a project

B The beginning and end of a job, are called events

C The activity which consumes maximum time, is called a node

D Logically and sequentially connected activities and events form a network

E None of these.

ANS:C - The activity which consumes maximum time, is called a node

Critical path is longest path but take minimum period.