Structural Design Specifications - Engineering

Q1:

Removal of props under

A slabs spanning upto 4.5 m is 7 days

B slabs spanning more than 4.5 m is 14 days

C beams spanning upto 6 m is 14 days

D beams spanning more than 6 m is 21 days

E all the above.

ANS:E - all the above.

No answer description is available.