Estimating and Costing - Engineering

Q1:

The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is

A Rs. 400

B Rs. 425

C Rs. 450

D Rs. 500

ANS:C - Rs. 450

E/W= 5 * 0.5 * 0.4 = 1 m3.

The Cost of E/W= 1 * 450 = 450.