Construction Management - Engineering

Q1:

The critical activity has

A maximum float

B minimum float

C zero float

D none of these.

ANS:C - zero float

C is correct, A critical path is the longest duration for the completion of a project. It is the path connected by all the critical activities. A critical activity cannot be delayed as delay in critical activity will increase the project completion time therefore critical activity or critical path have zero float or slack.