Waste Water Engineering

Q1: The design period of sewage treatment works in normally

A 5 - 10 years

B 15 - 20 years

C 30 - 40 years

D 40 - 50 years

ANS:B - 15 - 20 years

The design period of sewage treatment works typically ranges from 15 to 20 years. This design period accounts for the expected lifespan of the infrastructure, the projected population growth, changes in water usage patterns, and regulatory requirements. It allows for the treatment works to adequately serve the community over a significant period before requiring major upgrades or expansion. While some projects may have longer design periods depending on specific factors, the range of 15 to 20 years is commonly used in the planning and design of sewage treatment works.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.