Construction Management - Engineering

Q1:

The difference between the time avail-to do a job and the time required to do the job, is known as

A event

B float

C duration

D constraint.

ANS:B - float

Float =Time availed - Time Required.

Float shows the time within which you can delay an activity without affecting the overall duration of a project.