Q1: The dimensions of a rectangular settling tank are : length 24 m, width 6 m and depth 3 m. If 2 hour detention period for tanks is recommended, the rate of flow of sewage per hour, is

A 204 cu m

B 208 cu m

C 212 cu m

D 216 cu m

E 220 cu m

ANS:D - 216 cu m

Given:

  • Length of the tank = 24 m
  • Width of the tank = 6 m
  • Depth of the tank = 3 m
  • Detention period = 2 hours
The volume of the tank can be calculated as follows: Volume = Length × Width × Depth Volume = 24 m × 6 m × 3 m Volume = 432 cubic meters Now, with a detention period of 2 hours, the total volume of sewage that can be handled by the tank is: Total Volume = Volume of Tank × Detention Period Total Volume = 432 cubic meters × 2 hours Total Volume = 864 cubic meters To find the rate of flow of sewage per hour, we divide the total volume by the detention period: Rate of Flow = Total Volume / Detention Period Rate of Flow = 864 cubic meters / 2 hours Rate of Flow = 432 cubic meters per hour Therefore, the correct rate of flow of sewage per hour should be 432 cubic meters, not 216 cubic meters. It seems there might have been a mistake in the options provided or the calculation method.



img not found
img

For help Students Orientation
Mcqs Questions

One stop destination for examination, preparation, recruitment, and more. Specially designed online test to solve all your preparation worries. Go wherever you want to and practice whenever you want, using the online test platform.