Q1: The essential condition for the decompression of an activity is thatA the project time should change due to decompression
B after decompression the time of an activity invariably exceeds its normal time
C an activity could be decompressed to the maximum extent of its normal time
D none of the above
ANS:C - an activity could be decompressed to the maximum extent of its normal time Explanation: No answer description is available. |