| Q1: The essential condition for the decompression of an activity is thatA the project time should change due to decompression
  B after decompression the time of an activity invariably exceeds its normal time
  C an activity could be decompressed to the maximum extent of its normal time
  D none of the above
  ANS:C - an activity could be decompressed to the maximum extent of its normal time Explanation: No answer description is available. | 
 
             
                            