Estimating and Costing - Engineering

Q1:

The expected out turn for earth work in excavation in ordinary soil per mazdoor per day is

A 1.00 cubic meter

B 2.00 cubic meter

C 3.00 cubic meter

D 4.00 cubic meter

ANS:C - 3.00 cubic meter

As per I know it's 2.27 for ordinary soil.