Q1: The expected out turn of 2.5 cm cement concrete floor per manson per dayA 2.5 sqm
B
5.0 sqm
C
7.5 sqm
D
10 sqm
ANS:C - 7.5 sqm Option 3 : 7.5 square meter. |