Estimating and Costing - Engineering

Q1:

The expected out turn of 2.5 cm cement concrete floor per manson per day

A 2.5 sqm

B 5.0 sqm

C 7.5 sqm

D 10 sqm

ANS:C - 7.5 sqm

Option 3 : 7.5 square meter.

The expected outturn of 2.5 cm concrete floor is 7.50 square meters per mason.

The expected outturn for lime concrete in foundation or floor is 8.50 cubic meters per mason.

The expected out turn of earthwork in an excavation in ordinary soil is 3 cubic meters per mason.

Particulars of Item:

Expected

out-turn (sq. meter).

12 mm Plastering with cement or lime mortar is 8.0.
Pointing with cement or lime mortar is 10.0.
2.5 cm C.C. floor is 7.50.
Sawing hardwood is 4.00.
Sawing of softwood is 6.00.