Estimating and Costing - Engineering
Q1: The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length. The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by prismoidal formula, isA
3250 m3
B
3225 m3
C
3275 m3
D
3300 m3
ANS:B - 3225 m3 {(11+13)/2×0.5 + (11+21)/2×2.5}/2 × 150 = 3450cum is the right answer. |