- UPSC Civil Service Exam Questions - Section 1
- UPSC Civil Service Exam Questions - Section 2
- UPSC Civil Service Exam Questions - Section 3
- UPSC Civil Service Exam Questions - Section 4
- UPSC Civil Service Exam Questions - Section 5
- UPSC Civil Service Exam Questions - Section 6
- UPSC Civil Service Exam Questions - Section 7
- UPSC Civil Service Exam Questions - Section 8
- UPSC Civil Service Exam Questions - Section 9
- UPSC Civil Service Exam Questions - Section 10
- UPSC Civil Service Exam Questions - Section 11
- UPSC Civil Service Exam Questions - Section 12
- UPSC Civil Service Exam Questions - Section 13
- UPSC Civil Service Exam Questions - Section 14
- UPSC Civil Service Exam Questions - Section 15
- UPSC Civil Service Exam Questions - Section 16
- UPSC Civil Service Exam Questions - Section 17
- UPSC Civil Service Exam Questions - Section 18
- UPSC Civil Service Exam Questions - Section 19
- UPSC Civil Service Exam Questions - Section 20
- UPSC Civil Service Exam Questions - Section 21
- UPSC Civil Service Exam Questions - Section 22
- UPSC Civil Service Exam Questions - Section 23
- UPSC Civil Service Exam Questions - Section 24
- UPSC Civil Service Exam Questions - Section 25
- UPSC Civil Service Exam Questions - Section 26
- UPSC Civil Service Exam Questions - Section 27


UPSC Civil Service Exam Questions - Engineering
Q1: The loss of prestress due to shrinkage of concrete is the product ofA
modular ratio and percentage of steel
B
modulus of elasticity of concrete and shrinkage of concrete
C
modulus of elasticity of steel and shrinkage of concrete
D
modular ratio and modulus of elasticity of steel
ANS:C - modulus of elasticity of steel and shrinkage of concrete No answer description is available. |