Estimating and Costing

Q1: The most reliable estiamte is

A Detailed estimate

B Preliminary estimate

C Plinth area estimate

D Cube rate estimate

E None of these.

ANS:A - Detailed estimate

Yes, the detailed estimate is a more reliable estimate than others in this estimate each item of work is fully described with every detailed than other methods.