Estimating and Costing - Engineering
Q1: The most reliable estiamte isA
Detailed estimate
B
Preliminary estimate
C
Plinth area estimate
D
Cube rate estimate
E
None of these.
ANS:A - Detailed estimate Yes, the detailed estimate is a more reliable estimate than others in this estimate each item of work is fully described with every detailed than other methods. |