Engineering Economy - Engineering

Q1:

The project contractor relies on the cost of the estimate :

A for submission of a competitive bid for a lumpsum contract

B for a unit price contract

C for preparation of a definitive estimate to help negotiate contract.

D All of these

ANS:D - All of these

No answer description is available.