Construction Management - Engineering

Q1:

The time which results in the least, possible construction cost of an activity, is known

A normal time

B slow time

C crash time

D standard time.

ANS:B - slow time

Slow time means Increase in Labour Cost.

Crash time also increase the Labour Cost.

Answer should be Standard or Normal time from these options.