Q1: When slack of an activity is positiveA it represents a situation where extra resources are available and the completion of project is not delayed
B it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C the activity is critical and any delay in its performance will delay the completion of whole project
D any one of the above
ANS:A - it represents a situation where extra resources are available and the completion of project is not delayed Explanation: No answer description is available. |