Industrial Engineering and Production Management - Engineering

Q1:

When slack of an activity is positive

A it represents a situation where extra resources are available and the completion of project is not delayed

B it represents that a programme falls behind schedule and additional resources are required to complete the project in time

C the activity is critical and any delay in its performance will delay the completion of whole project

D any one of the above

ANS:A - it represents a situation where extra resources are available and the completion of project is not delayed

Explanation: No answer description is available.